How much work is done when 0.0080 C is moved through a potential difference of 1.5 V?

2 Answers

1 vote
.012 J is going to be your answer

User Rik Blacow
by
6.1k points
2 votes

Answer:

Work done, W = 0.012 Joules

Step-by-step explanation:

It is given that,

Charge, q = 0.0080 C

Potential difference, V = 1.5 volts

We need to find the work done. Potential difference is given by work done divided by charged moved. Mathematically, it is given by :


W=q* V


W=0.0080* 1.5\ V

W = 0.012 Joules

So, the work done by the charge is 0.012 Joules. Hence, this is the required solution.