What is the earliest that activity d can begin if activity a takes 3 days, activity b takes 5 days, and activity c takes 7 days?

User Jay Khan
by
4.8k points

1 Answer

4 votes
3 + 5 + 7 = 15

Activity D can begin after 15 days