The answer is 3,184 minutes.
According to the data, with a 75% learning curve, where the first unit is 1, the cumulative time to produce 500 units is 63.68 minutes.
Given that where the first unit took 50 minutes
Thus, the total time will be;
50 x 63.68
=3,184 minutes