Estimated manufacturing overhead $450,000
Estimated direct labor hours 150,000
Actual direct labor hours 180,000
Based on this information, the amount of overhead allocated to a job that used 300 direct labor hours is ________$
(Enter your answer as a whole number.)

1 Answer

6 votes

Answer:

$900

Step-by-step explanation:

The computation of the amount of the overhead allocated is shown below:

But before that the predetermined overhead rate is

As we know that

Predetermine overhead rate is

= Estimated manufacturing overhead ÷ estimated direct labor hours

= $450,000 ÷ $150,000

= $3

Now the overhead allocated is

= 300 direct labor hours × $3

= $900