Answer: 5h represents the number of hours Rob actually spent on the project.
Explanation:
Let Rob planned that he will spend x hours in his project.
According to the question,
He spent 25% more time on his project than he planned.
That is, his actual time = x + 25% of x = 125% of x
Again according to the question,
He spent an extra h hours on his project.
That is, 25% of x = h
![(25* x)/(100) = h](https://img.qammunity.org/2019/formulas/mathematics/middle-school/yk8cro2t3yc0apb51ox4bxcw10dgflrm5l.png)
![x=(100h)/(25)](https://img.qammunity.org/2019/formulas/mathematics/middle-school/6j8txhqfqr2wgvyf3xasrge9pi48rdh9nf.png)
x = 4h
Thus, his actual time = 125% of x = 125% of 4h =
= 5h
Which is the required expression.