186k views
5 votes
What would a risk be based on the following information: Marty is 60 percent certain that he can get the facility needed for $45,000, which is $7000 less than what was planned for

User Dustman
by
8.2k points

1 Answer

3 votes

Answer:

Marty is 60 percent sure that he can save the project the amount of $7,000 which means that the amount of $4,200 will tend to depict the 60 percent certainty Amount of the savings

Step-by-step explanation:

What would the risk be based on the information given in a situation where he is 60 percent sure that he can get the facility needed for the amounts of $45,000 in which the amount is lower that the amount of $7000 that was planned for is that Marty is 60 percent sure that he can save the project the amount of $7,000 which means that the amount of $4,200 which is simply calculated as (60%*$7,000) will tend to depict the 60 percent certainty Amount of the savings.

User Vaelyr
by
7.7k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories