186k views
5 votes
What would a risk be based on the following information: Marty is 60 percent certain that he can get the facility needed for $45,000, which is $7000 less than what was planned for

User Dustman
by
6.5k points

1 Answer

3 votes

Answer:

Marty is 60 percent sure that he can save the project the amount of $7,000 which means that the amount of $4,200 will tend to depict the 60 percent certainty Amount of the savings

Step-by-step explanation:

What would the risk be based on the information given in a situation where he is 60 percent sure that he can get the facility needed for the amounts of $45,000 in which the amount is lower that the amount of $7000 that was planned for is that Marty is 60 percent sure that he can save the project the amount of $7,000 which means that the amount of $4,200 which is simply calculated as (60%*$7,000) will tend to depict the 60 percent certainty Amount of the savings.

User Vaelyr
by
6.1k points