Manufacturing overhead was estimated to be $380,000 for the year along with 20,000 direct labor hours. Actual manufacturing overhead was $395,000, actual labor hours were 22,300. The predetermined overhead rate per direct labor hour would be:

User Tim Elhajj
by
3.8k points

1 Answer

8 votes

Answer:

the predetermined overhead rate per direct labor hour would be $19

Step-by-step explanation:

The computation of the predetermined overhead rate per direct labor is shown below:

Predetermined overhead rate per direct labor is

= (Estimated manufacturing overhead) ÷ (direct labor hour)

= ($380,000) ÷ ($20,000)

= $19

Hence, the predetermined overhead rate per direct labor hour would be $19