Answer: the volume of soil that must be excavated from the borrow pit to meet the project requirements is 228,523.48 m³
Step-by-step explanation:
First we determine the volume of solid required for compacted state using the relation;
V_t = V_v + V_s
V_t is the total volume need in its compacted state( 150,000 m³)
V_s is the volume of solid required for compacted state
V_v is the volume of voids in the compacted state( 0.49V_s)
so we substitute
150,000 = 0.49V_s + V_s
150,000 = 1.49V_s
V_s = 100,671.14 m³
Now we determine the volume of voids ( V_v) for natural material using the expression;
e = V_v / V_ s
given that e = 1.27
we substitute
1.27 = V_v / 100671.14
V_v = 127,852.34 m³
Now the total volume to be excavated from the barrow pit in Bellingham will be determined using the relation;
V_t = V_v + V_s
we substitute our values
V_t = 127,852.34 m³ + 100671.14 m³
V_t = 228,523.48 m³
Therefore, the volume of soil that must be excavated from the borrow pit to meet the project requirements is 228,523.48 m³