The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion for activity B.

A. 11 days


B. 6.5 days


C. 9 days


D. 8 days

The table shows five activities (in days) for a project. Use PERT (Program Evaluation-example-1
User Ahazzah
by
5.5k points

2 Answers

5 votes

Answer:

the answer is 8

Explanation:

i took the test

2 votes

Answer:

B. 6.5 days

Explanation:

The estimated time for completing an activity can be computed if we have optimistic time, most likely time and pessimistic time

The formula is:


T_e = (T_0+4T_m+T_p)/(6) \\where\\T_0 = Optimistic\ Time\\T_m = Most\ likely\ time\\T_p=Pessimistic\ time

For activity B:


T_0=3\\T_m=6\\T_p=12

Putting the values in the formula


T_e = (3+4(6)+12)/(6)\\T_e=(3+24+12)/(6)\\T_e=(39)/(6)\\T_e=6.5\ days

The correct answer is:

B. 6.5 days ..