All the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. How many hours would this job take if the num…
Ask a Question
Questions
Unanswered
Tags
Ask a Question
All the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. How many hours would this job take if the num…
asked
Jul 6, 2019
120k
views
5
votes
All the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. How many hours would this job take if the number of workers: increased 4 times
Mathematics
middle-school
MouzmiSadiq
asked
by
MouzmiSadiq
8.4k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
five and a half hours
Aboelnour
answered
Jul 10, 2019
by
Aboelnour
8.1k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
Related questions
asked
Apr 4, 2018
219k
views
All the members of a construction crew work at the same pace. six of them working together are able to pour foundation in 22 hours. how many hours would this job take if the number of workers:decreased
Arranjdavis
asked
Apr 4, 2018
by
Arranjdavis
7.9k
points
Mathematics
high-school
1
answer
2
votes
219k
views
asked
Oct 15, 2018
8.4k
views
All the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. How many hours would this job take if the number of workers: increased
Mary
asked
Oct 15, 2018
by
Mary
7.8k
points
Mathematics
college
1
answer
5
votes
8.4k
views
asked
Nov 18, 2019
204k
views
All the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. c How many hours would this job take if the number of workers increased
Niels Van Der Tak
asked
Nov 18, 2019
by
Niels Van Der Tak
7.3k
points
Mathematics
middle-school
1
answer
3
votes
204k
views
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.4m
questions
12.2m
answers
Categories
All categories
Mathematics
(3.7m)
History
(955k)
English
(903k)
Biology
(716k)
Chemistry
(440k)
Physics
(405k)
Social Studies
(564k)
Advanced Placement
(27.5k)
SAT
(19.1k)
Geography
(146k)
Health
(283k)
Arts
(107k)
Business
(468k)
Computers & Tech
(195k)
French
(33.9k)
German
(4.9k)
Spanish
(174k)
Medicine
(125k)
Law
(53.4k)
Engineering
(74.2k)
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qammunity.org