21.1k views
3 votes
A road crew can repave 1/56 miles of road each hour. They must repave a road that is 7/8 miles long. How long will it take the crew to repave the road?

User Rdonuk
by
8.2k points

1 Answer

5 votes

7/8 miles = 49 / 56 miles so it will take the road crew 49 hours to repave the road.