How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days?
asked
Nov 7, 2019
48.5k
views
0
votes
How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days?
Mathematics
high-school
DKSan
asked
by
DKSan
6.3k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
0
votes
8 workers can complete a task in 10 days, meaning the man-hours needed to this task is 80 man-hours.
Hence for 5 workers to complete the same task that require 80 man-hours, 80÷5= 16.
So, it will take 16 days for 5 workers to complete this task.
PsyGik
answered
Nov 13, 2019
by
PsyGik
6.6k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.4m
questions
9.9m
answers
Other Questions
How do you estimate of 4 5/8 X 1/3
Write words to match the expression. 24- ( 6+3)
Please solve the following equation. x-6x=56
whats the most accurate estimation of 65+77
Find the additive inverse of 18/23
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org