79.2k views
2 votes
what is tye minimum value for P=x-4y over the feasibility region defined by the constraints shown above?

what is tye minimum value for P=x-4y over the feasibility region defined by the constraints-example-1
User EyalS
by
8.7k points

1 Answer

3 votes

Answer:

The correct option is: -30

Explanation:

According to the given graph, the the leftmost vertex of the feasibility region is the intersecting point of lines
y=0 and
y= 3x+2

Now, solving the above two equations, we will get.......


0=3x+2\\ \\ 3x=-2\\ \\ x=-(2)/(3)

So, the co ordinate of the leftmost vertex will be:
(-(2)/(3),0)

From the given graph, the other vertices are:
(8,0), (8,2) and
(2,8)

Given objective function is:
P= x-4y

Now, we need to find the value of that objective function at each vertex. So....

For
(-(2)/(3),0) ,
P= -(2)/(3)-4(0)=- (2)/(3) \approx -0.67

For
(8,0) ,
P=8-4(0)=8

For
(8,2) ,
P=8-4(2)=8-8=0

For
(2,8) ,
P=2-4(8)=2-32=-30 (Minimum)

Thus, the minimum value of the objective function will be -30.

User Cronoklee
by
7.9k points