Risks commonly considered to understand project financing are:

User Gizgok
by
8.9k points

2 Answers

2 votes

Construction and completion risk, political and regulatory risk and expropriation and nationalization Risk, and environmental risk.

User Josh Edwards
by
7.4k points
1 vote

Answer:

– Construction risk

– Operational risk

– Supply risk

– Repayment risk

– Political risk

– Currency risk

– Authorizations risk

– Dispute resolution risk

Step-by-step explanation:

Financial risk refers to the possibility of loss or uncertainty about the return on an investment, making it impossible for the business to cover its financial obligations in a certain period of time and become unstable.