As per the given data
A task is completed by 30 persons in 4 days
we are supposed to find In how many days the same will be completed by 40 persons
Task is completed by 30 persons in 4 days, it mean
30 person does one fourth of the work in one day
1 person does
of the work in one day
So back to previous step,
work done by 40 person in one day =
![40*(1)/(120) =(1)/(3)](https://img.qammunity.org/2019/formulas/mathematics/high-school/kk3iebpndgou5n70npo7um6sl8b1yxf4a7.png)
Hence the number of days required to complete the work by 40 person =3