There are 3 types of Inventory as below:

1) Raw Material Inventory

2)Work in Process Inventory

3)Finished Goods Inventory

Schedule for Work in Process Inventory is as below:

Beginning Balance of Work in Process...................................................................XXX

Direct Materials

Beginning Balance of Direct Materials................................XXX

Add: Purchase of Raw Materials...........................................XXX

Total Raw Materials Available...............................................XXX

Less: Ending Balance of Raw Materials..............................(XXX)

Raw Materials Consumed.....................................................................XXX

Direct Labour...........................................................................................XXX

Manufacturing Costs

Indirect Labour....................................XXX

Factory Repairs...................................XXX

Factory Utility......................................XXX

Total Manufacturing Overhead............................................................XXX

Total Manufacturing Costs....................................................................................XXX

Total Cost of Work in Process..............................................................................XXX

Less: Ending Balance of WIP................................................................................(XXX)

Cost of Goods Manufactured................................................................................XXX