I'm only answering this one because I like the Three Stooges.
What's important in these questions is the rates, work per unit time, add up when we have multiple people.
Let c be Curly's rate in elephants per minute. Larry's rate is 1/10 elephants per minutes and Moe's is 1/6 elephants per minute. For the three of them to get done in three minutes means their collective rate is 1/3 elephants per minute:


Curly's rate is 1/15 th of an element per minute, so it would take him 15 minutes to paint an elephant.