A person-hour is a unit of measure representing one person working for one hour. A construction foreman estimates that it will take 2880 person-hours to build a new library. If 12 workers are scheduled to work on the project at the same time how many hours will it take to complete the project?

User Atif Ali
by
6.3k points

1 Answer

4 votes
We need 2880 person-hours and we have 12 people.

When we divide the work between them: 2880/12 = 240 hours required to complete.