There are 3 people who work full-time and are to work together on a project, but their total time on the project is to be equivalent to that of only one person working full-time. if one of the people is budgeted for 1/2 of his time to the prokect and a second person for 1/3 of her time, what part is the third workds time should be budgeted to this project

User TPoy
by
5.7k points

1 Answer

1 vote
The third person is budgeted to 1/4