HELP FAST. 40 points
A. ABCD

B. BCDA

C. CDAB

D. DABC

HELP FAST. 40 points A. ABCD B. BCDA C. CDAB D. DABC-example-1
User SANITH
by
6.5k points

1 Answer

2 votes
Based on the table, Problem A needs to be fixed in 24 hours (9 AM tomorrow). Problem B needs to be fixed in 24 hours (10 AM tomorrow). Problem C needs to be fixed in 12 hours (11 PM that night). Problem D needs to be fixed in 12 hours (11:30 PM that night). So the technician's order will be: C, D, A, B. This is the third choice.