Computer a can carry out an engineering analysis in 6 hours, but computer b can do the same job in 4 hours. how long does it take to complete the job if both computers work together?

1 Answer

4 votes
Computer A can carry out analysis in 6 hours. That means in an hour, computer A does
(1)/(6) of the job.

Computer B can carry out analysis in 4 hours. That means in an hour, computer B does
(1)/(4) of the job.

If both computers work together, in an hour they do:

(1)/(6)+ (1)/(4)

= (2)/(12)+ (3)/(12) \text{(equalize the denominators)}

= (5)/(12)
In an hour, they do
(5)/(12) of the job.

To finish the job, they need
(12)/(5) hours.

(12)/(5) hours
= 2.4 hours
= 2 hours + 0.4 hour
= 2 hours + 0.4 × 60 minutes
= 2 hours 24 minutes

They finish analysing in 2 hours 24 minutes