24 workers can do a work for 64 days, how many workers will do 48 days

User EvanDotPro
by
8.0k points

1 Answer

3 votes

If 24 workers ,,,,,,,,,,,,,,,,,,,,,64 days

then

x workers 48days

do CROSS MULTIPLICATION

64*x=24*48

64x=1152

Divide both sides by 64

x=18

18workers will do the work in 48 days