If a new sidewalk will be 5 feet wide, 100 feet long and filled to a depth of 9 inches (0.75 foot) with concrete how many cubic yards of concrete are needed
asked
Oct 17, 2019
230k
views
4
votes
If a new sidewalk will be 5 feet wide, 100 feet long and filled to a depth of 9 inches (0.75 foot) with concrete how many cubic yards of concrete are needed
Mathematics
college
Aftab Naveed
asked
by
Aftab Naveed
8.5k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
(5 ft)*(100 ft)*(0.75 ft) * ((1 yd)/(3 ft))³ ≈ 13 8/9 yd³
About
13.89 cubic yards
of concrete are needed.
Wawka
answered
Oct 22, 2019
by
Wawka
7.3k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
No related questions found
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.4m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qammunity.org