Answer:
Batch-level costs.
Step-by-step explanation:
The procurement cost is the cost that incurred for placing the orders with respect to the materials and supplier payment and these cost would be classified as a batch level cost as these cost are incurred in the batches
So as per the given situation the batch level cost would be taken into the consideration
And, the other options are incorrect