Answer:
$44,268
Step-by-step explanation:
Calculation for What is the total manufacturing overhead for the current product order if the firm uses a plantwide rate based on direct labor-hours
First step is to calculate the Plant-wide Overhead Rate using this formula
Plant-wide Overhead Rate = Total Overhead / Total Direct Labor Hours
Let plug in the formula
Plant-wide Overhead Rate = $632,400 / 4,800 hours
Plant-wide Overhead Rate = $131.75
Now let calculate the total manufacturing overhead for the current product order
Using this formula
Current product order Total Manufacturing Overhead = Plant-wide Overhead Rate * Direct Labor Hours
Let plug in the formula
Current product order Total Manufacturing overhead= $131.75 *336 hours
Current product order Total Manufacturing overhead= $44,268
Therefore the total manufacturing overhead for the current product order if the firm uses a plantwide rate based on direct labor-hours will be $44,268