Form a sequence that has two arithmetic means between -1 and 59. a. -1, 29, 29, 59 c. 19, -1, 59, 39 b. -1, 19, 39, 59 d. -1, 14, 29, 44, 59
asked
Jul 2, 2019
225k
views
4
votes
Form a sequence that has two arithmetic means between -1 and 59.
a.
-1, 29, 29, 59
c.
19, -1, 59, 39
b.
-1, 19, 39, 59
d.
-1, 14, 29, 44, 59
Mathematics
college
JoePerkins
asked
by
JoePerkins
7.5k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
7
votes
two arithmetic means between -1 and 59.
b.
-1, 19, 39, 59
Bristweb
answered
Jul 3, 2019
by
Bristweb
8.7k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
2
votes
The formula for solving the problem is as follow:
an = a1 + (n - 1)d
Where:
n = number of figure in the sequence = 4
d = difference between successive number =?
a1 = -1
a4 = 59
Insert the given values into the formula,
59 = -1 + (4 - 1)d
59 = -1 + 3d
59 + 1 = 3d
60 = 3d
d = 60/3 = 20
Therefore, d = 20. This implies that, there is a difference of 20 between successive numbers.
The number sequence is as follow:
-1, 19, 39, 59.
IlSavo
answered
Jul 8, 2019
by
IlSavo
7.8k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
No related questions found
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.4m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qammunity