Answer:
The project's payback period is 2.5 years.
Step-by-step explanation:
year cash flow comulative cash flow
0 -500 -500
1 150 -350
2 200 -150
3 300
payback period = 2 years + 150-300
= 2.5 years
Therefore, The project's payback period is 2.5 years.