Under a standard cost​ system, when recording the use of direct materials in the production​ process, the debit to​ Work-in-Process Inventory is​ _____

User Timothyjc
by
4.9k points

1 Answer

1 vote

Answer and Explanation:

standard quantity for actual production times standard cost per unit of direct material.