74.5k views
2 votes
The Flapjack Corporation had 7,872 actual direct labor hours at an actual rate of $12.21 per hour. Original production has been budgeted for 1,100 units, but only 984 units were actually produced. Labor standards were 7.1 hours per completed unit at a standard rate of $13.00 per hour. Round your answer to the nearest cent. The labor time variance is:

User Iguypouf
by
8.5k points

1 Answer

2 votes

Answer:

$11,512.80 unfavorable

Step-by-step explanation:

The computation of the labor time variance is shown below:

= (Standard Hours allowed - Actual hours) × Standard rate

= (984 units × 7.1 hour - 7,872 hours) × $13

= (6,986.40 hours - 7,872 hours) × $13

= 885.6 hours × $13

= $11,512.80 unfavorable

Simply we subtract the standard hours allowed from the actual hours and then multiplied it with the standard rate

User Ilya Tikhonov
by
7.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.