Answer:
d. $53
Step-by-step explanation:
The computation of the total standard cost is shown below
= Standard rate per pound × number of pounds + standard rate per direct labor hour × number of direct labor hour + standard overhead rate × number of direct labor hour
= $4 per pound × 2 pounds + $14 per direct labor hour × 1.5 labor hour + $16 per direct labor hour × 1.5 labor hour
= $8 + $21 +$24
= $53