70.3k views
5 votes
Coronado Industries has a materials price standard of $2.00 per pound. 4600 pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 4600 pounds, although the standard quantity allowed for the output was 3700 pounds. Coronado Industries's total materials variance is

1 Answer

3 votes

Answer:

$2,720 unfavorable

Step-by-step explanation:

The computation of the material price variance is shown below:

= Actual Quantity × Actual Rate - Standard Quantity × Standard Rate

= 4,600 pounds × $2.20 per pound - 3,700 pounds × $2 per pound

= $10,120 - $7,400

= $2,720 unfavorable

Since the standard cost is less than the actual cost so it is come to be unfavorable

User Woohyung
by
8.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.