125k views
5 votes
The signing of the project portfolio statement signals the transition from the high-level project initiating stage into the more detailed project planning stage.t/F

User Mjec
by
8.0k points

1 Answer

3 votes

Answer:

False

Step-by-step explanation:

Signing a project charter rarther than project portfolio signal the trasition of a project from high level initiating phse into a more detailed project planning stage.

cheers.

User NeroS
by
8.2k points