Answer:
The amount of factory overhead applied in October is $63,300.
Step-by-step explanation:
Goods finished + Oct 31 work in progress = direct materials + direct labor + oct 1 balance + factory overhead
360,000 + 21,000 = 96,700 + 201,000 + 20,000 + Factory Overhead
381,000 = 317,700 + Factory overhead
Factory overhead = $63,300
Therefore, The amount of factory overhead applied in October is $63,300.