Answer:
option (B) 100
Step-by-step explanation:
Data provided in the question:
Number of days supplier takes to deliver an order once it has been placed i.e the lead time = 25 days
Standard deviation of daily demand = 20
Now,
Standard deviation of usage during lead time
= Standard deviation of daily demand × √(Lead time)
= 20 × √25
= 20 × 5
= 100
Hence,
The answer is option (B) 100