Forte Co., had 3,000 units of work in process on April 1 that were 60% complete. During April, 11,000 units were started and as of April 30, 4,000 units that were 40% complete remained in production. How many units were completed during April?

a. 12,200.
b. 10,000.
c. None of the answers is correct.
d. 9,800.
e. 11,000.

1 Answer

5 votes

Answer:

b. 10,000.

Step-by-step explanation:

The number of units completed in April is given by the number of units on April 1st (3,000) added to the number of units started during April (11,000) minus the number of units still in production on April 30th (4,000):


\begin{array}{ccc}Starting\ n^o\ of\ units&3,000\\Units\ started\ in\ April&11,000\\Units\ not\ completed\ in\ April&(4,000)\\Units\ completed\ in\ April&10,000\end{array}

10,000 units were completed during April.