Answer:
Labour rate variance
= (Standard rate - Actual rate) x Actual hours worked
= ($19 - $18) x 3,000 hours
= $3,000(U)
Actual rate = Actual direct labour cost
Actual direct labour hours worked
Actual rate = $54,000
3,000 hours
Actual rate = $18 per direct labour hour
Step-by-step explanation:
Labour rate variance is the difference between standard rate and actual rate multiplied by actual direct labour hours worked. Actual direct labour hours worked is calculated as actual direct labour cost divided by actual direct labour hours worked.