Answer: Cash break - even point
Step-by-step explanation:
The NPV (net present value) is negative $120,000. Whereas, the initial cash outlay requires $120,000.
The cost of the project is equal to the inital cash flow of the project. Therefore, the project is expected to operate at cash break - even point.