Answer:
Overhead application rate
= Budgeted overhead
Budgeted machine hours
= $266,400
18,500 hours
= $14.40 per machine hour
Overhead applied
= Overhead application rate x Actual machine hours
= $14.40 x 19,050 hours
= $274,320
Under-applied overhead
= Overhead applied - Actual factory overhead
= $274,320 - $287,920
= $13,600
Step-by-step explanation:
In this question, there is need to determine the overhead application rate, which is the ratio of budgeted factory overhead to budgeted machine hours. Then, we will calculate the overhead applied, which is overhead application rate multiplied by actual machine hours. Under-applied overhead is the difference between overhead applied and actual factory overhead. .