Answer:
amount of work done = -1.77 J
Step-by-step explanation:
given data
mass = 0.25 kg
speed = 5 m/s
height = 2m
to find out
amount of work done by the water on the ball bearing
solution
we get here potential energy when ball fall
potential energy = mgh
potential energy = 0.25 × 9.8 × 2
potential energy = 4.9 J
and that lose potential energy gain by kinetic energy that is express as
kinetic energy = 0.5 × m × v²
kinetic energy = 0.5 × 0.25 × 5²
kinetic energy = 3.13 J
so we get now work done that is
work done = kinetic energy - potential energy
work done = 3.13 J - 4.9 J
amount of work done = -1.77 J