1- Total Cost of Project = (W-1) 600,000 $
2-Total Benifits Received = (W-2) 575,000 $
3- Overall ROI of Project= (W-3) 96%
Step-by-step explanation:
(W-1) It includes one time cost incurred and paid initially. Following Cost are included in it.
Module Cost = $ 400,000
User license = $ 50,000 (1000*50)
Hardware = $ 100,000
Labor Cost = $ 50,000
(W-2) Total benifits received includes all cost saving - incremental costs. It is calculated as follow.
Liecense fee per years = $ (25,000)
Resource saving = $ 350,000
Employee saving = $ 100,000
Acounting staff cost = $ 750,000
saving
Project Cost = $ (600,000) *Depreciation
(W-3) ROI= W-2/W-3
= 575,000/600,000