In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?

User Knutole
by
5.1k points

1 Answer

5 votes

Answer:

The early finish time for activity T is 29

Step-by-step explanation:

Activity time for T is 7

Assuming the early start time is 22,

Early finish time = 22 + 7 = 29