____________ is accomplished by reviewing all change proposals, estimating their impact on project goals wherever appropriate, approving or declining changes, and managing changes to deliverables, schedules, budgets, and the project management plan.

1 Answer

5 votes

Answer:

Integrated change control

Step-by-step explanation:

Integrated change control is a process in project management that involves managing all changes that may occur during the project.

It involves reviewing the requests for change from different areas of the organization, and deciding whether to accept or reject these requests.

Change requests may include; changes to the budget, processes, project timeline or the project plan.

If a request for change is accepted, then it's implementation must be monitored and controlled.