32.0k views
3 votes
The per-unit standards for direct materials are 2 pounds at $5 per pound. Last month, 11,200 pounds of direct materials that actually cost $53,000 were used to produce 6,000 units of product. The direct materials quantity variance for last month was

1 Answer

5 votes

Answer:

$4,000 favorable

Step-by-step explanation:

The computation of the material quantity variance is shown below:

= Standard Price × (Standard Quantity - Actual Quantity)

= $5 × (2 pounds × 6,000 units - 11,200 pounds)

= $5 × (12,000 pounds - 11,200 pounds)

= $5 × 800

= $4,000 favorable

Simply we deduct the actual quantity from the standard quantity and the difference is multiplied with the standard price so that the correct variance can be computed

User Eran
by
7.0k points