Answer:
The answer is C.
Step-by-step explanation:
The CFO has only sounded the alarm about an over-budgeted project. He brought the fact to the attention of the project manager. The memo does not make any change in responsibilities, it only calls for keeping the project performance within planned limits. In principle, it´s safe to assume that the project manager will continue to be in charge.