120k views
0 votes
The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1800 units, the actual direct labor cost was $48000 for 3000 direct labor hours worked, the total direct labor variance is: a. $6000 unfavorable. b. $1800 unfavorable. c. $3750 unfavorable. d. $6000 favorable.

User Tesdal
by
5.5k points

1 Answer

4 votes

Answer:

The correct answer is D.

Step-by-step explanation:

Giving the following information:

The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1800 units, the actual direct labor cost was $48000 for 3000 direct labor hours worked.

We need to calculate the total direct labor variance, using two formulas:

Direct labor efficiency variance= (SQ - AQ)*standard rate

Direct labor efficiency variance= (1,800*2 - 3,000)*15= $9,000 favorable

Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity

Direct labor rate variance= (15 - 48,000/3,000)*3,000= $3,000 unfavorable

Total direct labor variance= 9,000 - 3,000= $6,000 favorable

User Ridham Tarpara
by
6.5k points