Answer: phase 2.
The business continuity relocation plase
Explanation: the continuity plan consists of four stages.
1. Initial Response
2. Relocation
3. Recovery
4. Restoration
Initial response deals with Initial Notifications,
Business Continuity Team (BCT) activation,
Business Unit personnel activation
Initial BCT briefing,
Review of recovery strategies for implementation,
Implementation of Business Continuity Action Plan.
The business continuity relocation plase deals with The relocation phase involves mobilization of resources and relocation of equipment and personnel to Alternate Facilities or Redundant Sites. And this seems to be the stage that the industry is at.