Additional information
Loading Method Single Pusher Tandem Pusher
Back-Track 1.5 1.4
Chain or Shuttle 1.0 0.9
Answer:
(a) 3 back-trucks and 2 chains
(b) 2491 BCY/hr
Step-by-step explanation:
(a)
The number of scrapers per pusher
Number of pushers needed
(b)
Production=(Number of pushers* Number of scrappers* Production per scrapper)/ Required number of pushers