Answer:
a. 83.02%
b. 76.52%
Step-by-step explanation:
The computations are shown below:
a. Facility's efficiency rate = Actual output × 100 ÷ Effective capacity
= 88 × 100 ÷ 106
= 83.02%
b. Facility's utilization rate = Actual output × 100 ÷ Design capacity
= 88 × 100 ÷ 115
= 76.52%