The project plan is supported by:

1. The work breakdown structure, the budget, and the work packages.
2. The work breakdown structure, the budget, and the schedule.
3. The work breakdown structure, the work packages, and the schedule.
4. The work breakdown structure, the schedule, and the contingency plan.

User Zev
by
8.0k points

1 Answer

5 votes

Answer:

3. The work breakdown structure, the work packages, the budget and the schedule.

Step-by-step explanation:

Supporting plans for the Project plan includes:

  • Resource plans
  • Communication Plans
  • Risk management plans
  • Quality plans
  • Budget
  • Procurement plans
  • Scope
  • Delivery schedule

Based on this we can say that option 3 is correct since it includes budget & schedules.