Answer:
2.95 minutes
Step-by-step explanation:
For computing the takt time minutes per cycle, first we have to determine the available time which is shown below:
= Total work time - break time
= 358 minutes - 98 minutes
= 260 minutes
The 98 minutes is come from
2 × 19 minutes = 38 minutes
1 hour lunch = 60 minutes
Total break time = 98 minutes
Now the takt time minutes per cycle would be
= Total available time ÷ number of jobs in a day
= 260 minutes ÷ 88 jobs
= 2.95 minutes